Lean Manufacturing
Coursework
Read the Farm Equipment International data set and:
- Produce a door-to-door value stream map of the current manufacturing
process.
- Outline and answer the eight key questions for the future state design.
- Thereby produce a future state map detailing the processes necessary
to operate the factory according to lean manufacturing principles.
- Produce an implementation plan for the company to move from
present state to future state.
Notes:
This coursework is intended to measure the following learning outcomes:
reflect on the significance of lean theory and the application of key lean thinking
principles;
critically analyse lean thinking in different engineering sectors;
formulate innovative proposals based on detailed knowledge of the tools and
techniques relating to the implementation of lean thinking;
Farm Equipment International
Farm Equipment International (FEI) produces components and sub-assemblies for
agriculture. Here, we are considering one product family, hydraulic control sections.
These are produced in several configurations for different tractors and markets. The
market for hydraulic control sections covers both original-equipment tractor
assemblers and the aftermarket repair and overhaul businesses that support the
agricultural industry worldwide.
As the company offers a wide variety of possible configurations, and the fact that the
exact configuration each customer requires can vary from order to order, hydraulic
control sections are made to order. A hydraulic control lever currently takes 27 days
to go through the factory. This production lead time and a large order backlog have
resulted in FEI to quote a 60 day lead time to customers. Unfortunately, FEI’s
original-equipment customers can not predict their exact requirements more than 2
weeks before use. As a result they make frequent changes to the detail of their orders
2 weeks before delivery. These changes lead to frequent expediting of batches at the
FEI factory.
Production Control at FEI releases customer orders to the factory approximately in the
sequence that they are received, the shop floor supervisors and operators “batch” the
orders together by configuration in an attempt to reduce the number of changeovers.
This also leads to expediting of orders.
The product
A hydraulic control section is a metal tube with a cast connector welded to
each end.
Hydraulic control sections are available in 20 different lengths, 2 diameters,
and with 3 different types of connectors. Each end of a hydraulic control
section can have a different connector. This means that FEI can supply 240
different finished hydraulic control sections.
Customer requirements
24000 hydraulic control sections per month.
Order size varies from 20 pieces up to 200 pieces. Average order size is 50
pieces.
Up to 5 hydraulic control sections per box.
Several shipments each day by truck to different customers.
Each order from each customer varies in quantity and configuration.
FEI requires orders to arrive 60 days before shipping of finished hydraulic
control sections.
Customers may change the mix of configurations up to 2 weeks before the
shipping date.
Production Processes
All the hydraulic control sections follow the same basic factory routing:
Cut tube Weld Weld Remove Paint Assembly
1st end 2nd end flash (contractor)
Machine Castings
FEI’s routing for producing hydraulic control sections is to cut a metal tube to
length, weld the connectors in place, deflash (remove the excess weld
material), painting (done at an external contractor’s premises), and finally
assembly of the connectors. The cast connectors are also machined at FEI’s
factory. Finished hydraulic control sections are shipped to customers daily.
Switching between tube lengths requires a 15 minute changeover at the
cutting, welding and deflash workstations.
Switching between tube diameters takes a 60 minute changeover at the cutting,
welding and deflash operations. This longer changeover is mostly due to a “1st
off” quality control inspection after such a changeover.
Switching between each of the three types of cast connectors takes a 2 hour
changeover at the machining operation.
Tubes are supplied by Kentish Tube Systems Ltd. The lead time for obtaining
tubes is 4 months (16 weeks). Kentish Tube Systems Ltd. deliver products
every 2 weeks.
Raw castings for the end connectors are supplied by Essex Castings Ltd. The
lead time for obtaining castings is 3 months (12 weeks). Essex Castings Ltd.
deliver products every 2 weeks.
Work Time
20 days in a month.
2 shifts per day in each department.
8 hours per shift, overtime added if necessary.
Two breaks each shift, 15 minutes per break.
oManual processes stop for breaks
oLunch is not paid.
FEI Production Control
Receives customer orders 60 days from shipment, and enter them to MRP
system.
Generates a “shop order” per customer order. This follows the product through
the entire production process.
Release shop orders to the factory 6 weeks before the shipment date to
accelerate MRP’s ordering of tubes and castings.
Issue a daily production list to supervisors in production departments.
Supervisors schedule shop orders through their department.
Receives customer configuration changes 2 weeks before shipment and
advises department supervisors to expedite orders as necessary.
Issues daily shipping schedule to Despatch Department.
Process Information
- Cutting (the saw cuts tubes and rods for many FEI product families).
Manual process, 1 operator
Cycle time = 15 seconds
Changeover time = 15 minutes (length), 60 minutes (diameter)
Reliability = 100%
Inventory
- 20 days of uncut tubes
- 5 days of cut tubes.
- Welding workstation 1 (dedicated to the hydraulic control sections product
family)
Welds the first machined casting to the tube
Automatic process, with operator load and unload external to the
machine cycle
Cycle time:
- Operator = 10 seconds
- Machine = 30 seconds
Changeover time = 15 minutes (length), 60 minutes (diameter)
Reliability = 90%
Inventory = 3 days of welded sections.
- Welding workstation 2 (dedicated to the hydraulic control sections product
family)
welds the second machined casting to the tube
Automatic process, with operator load and unload external to the
machine cycle
Cycle time:
- Operator = 10 seconds
- Machine = 30 seconds
Changeover time = 15 minutes (length), 60 minutes (diameter)
Reliability = 80%
Inventory = 3 days of welded sections.
- Deflash workstation (dedicated to the hydraulic control sections product
family)
Automatic process, with operator load and unload external to the
machine cycle
Cycle time:
- Operator = 10 seconds
- Machine = 30 seconds
Changeover time = 15 minutes (length), 60 minutes (diameter)
Reliability = 100%
Inventory = 5 days of deflashed sections.
- Painting (hydraulic control sections are shipped to an outside contractor for
painting)
Painting lead time = 2 days
One daily truck pickup of unpainted sections and drop-off of painted
sections
Observed inventory:
- 2 days at the painter
- 6 days of painted sections at FEI.
- Connector assembly (dedicated to the hydraulic control sections product
family)
Manual process with 6 operators
Total Work Time per Piece = 195 seconds
Changeover time = 10 minutes fixture swap
Reliability = 100%
Observed finished goods inventory in warehouse = 4 days of finished
hydraulic control sections.
- Machining of Castings (dedicated to the hydraulic control sections product
family)
Automatic machining process with one machine attendant
Cycle time = 30 seconds
Changeover time = 2 hours
Reliability = 100%
Observed inventory:
- 20 days of raw castings from the supplier
- 4 days of machined castings.
- Despatch department
Removes parts from finished goods warehouse and stages them for
truck shipment to customers.
Do you want your assignment written by the best essay experts? Order now, for an amazing discount.
You May Also Like This:
- Manufacturing Budget Analysis
- Manufacturing and Material
- application of Process Costing of a manufacturing company
- Winsome Manufacturing Company
- manufacturing overhead
- the appropriate ABC groups of inventory items
- Practice Problems: Inventory Management
- Advanced computer aided design techniques
- Traditional vs. ABCLO2
- Preparing the T-accounts for raw materials inventory
- inventory balances
- Analysis of stockholders’ equity
- Hoover, Inc., uses a job-order coding system. The company’s inventory balances on February 1, the start of its fiscal year
- Shamrock Manufacturing
- Case Study, Chapter 70, Management of Patients With Oncologic or Degenerative Neurologic Disorders Ida Parker, a 67-year-old patient, was admitted to the intensive care unit with the diagnosis of lung cancer and underwent a left lower lobectomy. The
- children vaccination
- Calculating Inventory
- Discussion Questions
- Supply chain management.
- Somerset Furniture Company’s Global Supply Chain
- INDIVIDUAL ASSIGNMENT
- Case Study, Chapter 42, Management of Patients With Musculoskeletal Disorders ane Wagner, a 22-year-old patient with no previous medical history, presents to the emergency department
- Pollution Prevention
- Developing a managerial intervention by engaging the following prompt
- Inheritance and Polymorphism
- Product Development
- Consumers and the Law
- Project Paper: Tesla Motors
- Aurora Textile Company
- Revenue Cycle