Identify the tender sum that the contractor should submit for the project. This should be broken down into the following:
- Temporary works and site overheads.
- Costs of supervisory and managerial staff
- Costs of skilled labour
- Costs of unskilled labour
- Costs of construction plant
- Costs of materials procured locally
- Costs of imported materials and components
- Costs of imported equipment
- Contingencies
- Head office overhead costs
- Profit margin
The above costs should be broken down into a cash flow schedule for each month of the project commencing from the time when the contract was signed through to the date for commencement on site to the completion date and the date for final settlement.
The above should be compared with the expected cash inflow from the mobilization payment, interim certificates and final payment to form a cumulative cash flow schedule.
All the above should be presented in local currency. Current exchange rates can be computed as for Part II below.
Part II
Take account of the following economic changes and revised the expected profit margin and the cash flow schedule:
- Local inflation
- Devaluation of the local currency against other currencies
- Pound Sterling
- Euro
- US Dollar
- South African Rand
- World interest rates
- Time and cost escalation
The incidence of inflation, currency fluctuations, interest rates and time and cost escalation will be determined by random numbers. These will be provided in a table within the project brief and can be read off the row corresponding to the last two digits on the student’s matriculation number.
Supervisory Staff | Skilled Labour | Unskilled Labour | Local Materials | Plant from USA | Components from France | Equipment from South Africa | ||
£ Sterling | D Dalasi | D Dalasi | D Dalasi | $ Dollars | € Euros | R South Africa | ||
1 | Temporary works and site overheads. | DJF 306,000,000 | DJF 1,989,000,000 | DJF 306,000,000 | $1,815,600 | € 2,958,000 | ||
2 | Costs of supervisory and managerial staff | £30,600,000 | ||||||
3 | Construction of Quay and Jetties | DJF 982,500,000 | DJF 7,860,000,000 | DJF 6,877,500,000 | $34,977,000 | R 70,740,000 | ||
4 | Construction of Rail Links | DJF 642,600,000 | DJF 2,754,000,000 | DJF 3,488,400,000 | $16,340,400.00 | € 3,549,600 | R 39,657,600 | |
5 | Construction of Roads | DJF 150,000,000 | DJF 1,425,000,000 | DJF 1,312,500,000 | $4,450,000.00 | € 2,175,000 | R 18,900,000 | |
6 | Warehouses | DJF 112,500,000 | DJF 281,250,000 | DJF 506,250,000 | $667,500.00 | € 1,087,500 | R 4,050,000 | |
7 | Storm Culverts and River Diversions | DJF 112,500,000 | DJF 675,000,000 | DJF 1,012,500,000 | $3,204,000.00 | € 1,740,000 | ||
8 | Landscaping | DJF 114,750,000 | DJF 1,262,250,000 | DJF 459,000,000 | $4,085,100.00 | € 1,109,250 |
Assumed Exchange rates for DJF (Part I of assignment) | Revised Exchange rates for DJF (Part 2 of assignment) | Inflation per annum | Interest Rates | Cost escalation (contract sum) | Time overrun | ||||||
£Sterling | $US | € Euro | Rand | £Sterling | $US | € Euro | ZARand | % | % | % | weeks |
157 | 112 | 148 | 11.1 | 170 | 121 | 160 | 12.1 | 10.7 | 5.5 | 6.8 | 5 |
Place your order now for a similar paper and have exceptional work written by our team of experts to guarantee you A Results
Why Choose US:
6+ years experience on custom writing
80% Return Client
Urgent 2 Hrs Delivery
Your Privacy Guaranteed
Unlimited Free Revisions
You May Also Like This:
- CASH FLOW ESTIMATION AND CAPITAL BUDGETING
- Discounted Cash Flow Model
- Estimating Project Cash Flows
- Manufacturing and Material
- Prepare a statement of cash flows using the direct and the indirect method
- Flow and Resonance
- Future Cash Flows
- long-term US Treasury yields
- Case Study in Finance
- International Financial Management
- resource-constrained network
- Aurora Textile Company
- case report
- accounting
- Project Planning, Control and Risk
- Economic Choice & Economic Decision Making
- Project
- economic reasoning underlying conclusions about current events.
- Economy
- financial plan
- CASE 9-30 Earrings Unlimited
- solar energy
- Using the supply and demand analysis of the market for reserve
- Assignment
- Unemployment
- Compound Interest
- alculating Present Values Imprudential, Inc., has an unfunded pension liability of $750 million that must be paid in 20 years
- Home Builder Supply
- Supply chain management.
- mutual fund investment plan